WORK ARCHITECTURE — WORKFLOW MAP
DRAFT — PENDING OPERATOR REVIEW

Office Bidding and Pre-Construction Workflow

Trigger
Starts when a new opportunity and the owner's drawing set reach the office
End state
Ends when the construction agreement is signed with final dollar amounts
7 phases15 processes53 core activities19 open questions
Phase One

Opportunity Intake and Evaluation

Principal
PROCESS 1.1

Opportunity Intake Process

Role

Principal

Trigger

Starts with a call from a prospect or a repeat developer

End state

Ends when the drawings are in hand and the super knows a job is coming

PROCESS 1.2

Opportunity Evaluation Process

Role

Principal

Trigger

Starts when the drawing set arrives

End state

UNKNOWN — not in source

Phase Two

Historical Budget Development

Principal
PROCESS 2.1

Job Workspace Setup Process

Role

Principal

Trigger

Starts with the go decision

End state

Ends when the job has its own budget workbook and project

PROCESS 2.2

Budget Build and Specification Process

Role

Principal

Trigger

Starts when the job budget workbook exists

End state

UNKNOWN — not in source

Phase Three

Budget Presentation and Agreement

Principal
PROCESS 3.1

Budget Presentation and Agreement Process

Role

Principal

Trigger

UNKNOWN — not in source

End state

Ends when the agreement is signed and paid, or a repeat developer commits verbally

Phase Four

Permitting and Project Release

Principal
PROCESS 4.1

Permit Submission Process

Role

Principal

Trigger

Starts with the signed agreement, once the plans are far enough along

End state

Ends when the permit is approved, though dirt may move when approval is about a week out

PROCESS 4.2

Drawing Refinement Process

Role

Principal

Trigger

Starts with the signed agreement when the budget was priced off a design set

End state

Ends when the drawing basis for sub pricing is settled

PROCESS 4.3

Field Release Process

Role

Principal

Trigger

Starts when plans go to the city

End state

Ends when the super starts the schedule

Phase Five

Subcontractor Solicitation and Award

Principal
PROCESS 5.1

Scope of Work Preparation Process

Role

Principal

Trigger

Starts when the drawing basis is settled

End state

Ends when every trade that needs a scope has one and the roster is set

PROCESS 5.2

Bid Solicitation Process

Role

Principal

Trigger

Starts when scopes are done

End state

Ends when every solicited scope has a price back

PROCESS 5.3

Bid Award Process

Role

Principal

Trigger

Starts when sub prices come back by email

End state

Ends when awarded subs have signed their scopes

Phase Six

Selections and Material Pricing

Principal
PROCESS 6.1

Owner Selections Process

Role

Principal

Trigger

Starts with unselected finishes after the budget meeting

End state

Ends when real pricing for every pick is in the final budget

PROCESS 6.2

Material Takeoff Process

Role

Principal

Trigger

Starts when scopes go out

End state

Ends when Slate-supplied quantities are priced for the final budget

Phase Seven

Final Budget and Contract Execution

Principal
PROCESS 7.1

Final Budget Assembly Process

Role

Principal

Trigger

Starts when all sub bids, supplier quotes, and priced takeoffs are back

End state

Ends when the owner accepts the number; how that happens is unknown (see 7

PROCESS 7.2

Contract Execution Process

Role

Principal

Trigger

Starts when the owner accepts the final budget

End state

Ends when the owner signs

WORKFLOW MAP REVIEW

Notes & Assumptions

Sources and confidence

  • Main source: the 2026-07-21 office and bidding session (OFF-F1 to OFF-F78). High confidence.
  • Business context: the 2026-05-19 discovery conversation (DISC-F6, F7, F11, F12, F14, F15).
  • Tool changes: the 2026-08-11 tech-stack session (STACK-F5 to F31). JobTread and Quo were confirmed by Patrick on 2026-08-25.
  • Field-side evidence: Tom Kirk, 2026-08-05 (TOM-F4 to F8, F11, F12, F48) and Connor Fields, 2026-08-06 (CON-F2 to F8).
  • Transcripts garble product names. Clean names are used: Asana, Instagantt, JobTread, Quo, Adaptive, Granola, ConX under Houzz, Buildertrend, OG&E.
  • 41 active where the work happens today, 14 gap where a step should exist and does not.

Why the reduction is below the typical band

Some work in this map also appears in other maps.

Old-to-new activity map

DraftFinalNote
1.1.1 to 1.1.3; 1.1.41.1.1; 1.1.2M1
1.2.1 to 1.2.5; 1.2.61.2.1; 1.2.2M2
2.3.1, 2.3.2; 2.4.x2.2.4; 2.3.xM3, process merge and renumber
3.1.1 to 3.1.4; 3.2.1 to 3.2.33.1.1; 3.1.2 to 3.1.4M4, process merge and renumber
4.1.1, 4.1.2; 4.1.3, 4.1.44.1.1; 4.1.2, 4.1.3M5
6.1.2, 6.1.3; 6.1.46.1.2; 6.1.3M6
7.1.1, 7.1.2; 7.1.37.1.1; 7.1.2M7
(new)1.1.3, 1.2.3, 2.1.4, 2.2.5, 2.2.6, 3.1.5, 3.1.6, 5.3.4, 5.3.5, 7.1.3Added; all other numbers unchanged

Structure notes

  • One owner. Almost everything is done by the Principal. Phase breaks mark real gates, not changes of hands.
  • Where work changes hands: Owner (Phases 3 and 4), subs and suppliers (5 and 6), Office Manager (6.2), super (4.3).
  • The super's workflow starts in Phase 4 and runs alongside Phases 5 to 7.
  • Phase 3 has one process. It stays a phase because it holds the money line.
  • Phases 1 to 3 are unpaid; 4 to 7 are paid. See question 2.
  • One bid sheet. The Phase 2 budget and the Phase 7 final budget are the same tab at two points in time.
  • Phase 6 runs alongside Phase 5. Ops map is sequential, so they are listed in order.
  • Shared processes: 2.1, 2.3, 4.3, 5.2, 6.2, 7.2 (rows 1 to 6 in `_process-registry.md`). Unhappy paths are thin; see questions 6 to 8.

Assumptions to verify

  • Role names. `Principal` is the business owner. `Owner` is the client. Superintendent maps to Site Supervision. Confirmed once, in the Field Execution map (question 4).
  • The office manager is a single point of failure on cost data. One person keeps the unit costs every budget is built from.
  • Acceptance is mostly undefined. Nobody has said how the owner accepts the one-pager, what opens paid work for repeat developers, or how the super confirms the field release.
  • Budget ownership. Budget and scope ownership is unclear. Patrick says he does nearly all of it. Tom says he did it on one live job. See question 3.
  • Sub-functions are tentative. Fourteen across 55 activities; largest are Budget Estimating (10), Contract Administration (8), Bid Management (8).
  • Estimating volume. About five bids a year against seven to eight jobs finished, so some repeat jobs may skip full bidding. Unresolved.

Rule deviations

[Rule deviation] Twelve activity titles name the person receiving something (1.1.2, 2.1.4, 3.1.2, 3.1.3, 3.1.4, 3.1.6, 4.1.2, 4.2.1, 5.3.2, 6.1.1, 7.1.3, 7.2.2). Eleven name an outside party; 1.1.2 names the super. Accepted, following the Paxus maps.

[Rule deviation] Phase breaks mark gates, not changes of hands, because one role does nearly everything. Accepted.

[Rule deviation] The release to the super is written in Phase 4 (the sending side) because the receiving side lives in another map. Accepted.

Tool transitions

Tool in this workflowWhere it appearsDecided targetStatus
AsanaJob project, tasks, schedule template (2.1.2, 2.1.3, 4.3.2)JobTreadDecided. Running jobs finish in Asana
InstaganttSchedule editing (4.3.2)JobTread GanttDecided. Retires with Asana
Excel and Google SheetsMaster budget, bid tracking, sub database (2.1.1, 2.2.2, 2.3.1, 5.1.3, 5.2.2, 6.1.3, 7.1.1)JobTreadDecided for most sheets; master budget open
Personal cellCalls and texts (1.1.1, Phases 5 and 6)QuoDecided. Number porting undecided
In-person conversationSuper notification and field release (1.1.2, 4.3.1)Slack, channel per jobProposed, after JobTread and Quo
Gmail and Google DriveDrawings, bids, quotes, agreements (throughout)StayingNo replacement
AdaptiveFee invoicing, city fees (3.1.4, 4.1.1)StayingUntouched
ConX under HouzzTakeoffs (2.2.1, 6.2.1)No decisionStays by default. One super prefers Bluebeam

Granola is available but no meeting here is recorded today. JobTread selections is the target for 6.1.1.

FOR THE MAPPING SESSION

All open questions (19)

Phase 1: Opportunity Intake and Evaluation

Jump to phase ↑
  • Q14

    Is a declined opportunity recorded anywhere today?

Phase 2: Historical Budget Development

Jump to phase ↑
  • Q11

    Is the spec one-pager a template today?

  • Q16

    Should the budget carry a visible contingency line?

  • Q17

    Should a second person, likely the office manager, review the budget before it is presented?

Phase 3: Budget Presentation and Agreement

Jump to phase ↑
  • Q4

    On repeat-developer jobs, is the owner's verbal yes at the budget meeting the go-ahead to spend sub time?

  • Q5

    Is there a set path when the presented number is far above the owner's ceiling?

Phase 4: Permitting and Project Release

Jump to phase ↑
  • Q6

    Should the office own permit tracking as a status field on the job?

  • Q7

    Should the field release become a written list (plans, budget, permit status, what the field owns) that the super confirms in writing with a schedule due date?

Phase 5: Subcontractor Solicitation and Award

Jump to phase ↑
  • Q8

    Is price variance the whole rule for which trades get a formal scope?

  • Q18

    Do returned bids get checked against each other for scope gaps today?

  • Q19

    Is sub insurance and license re-verified on each job today?

Phase 6: Selections and Material Pricing

Jump to phase ↑
  • Q9

    Is the split that the office manager takes repeatable takeoffs and the principal keeps the judgment-heavy ones?

Phase 7: Final Budget and Contract Execution

Jump to phase ↑
  • Q1

    Is the signed construction agreement the single end of this workflow?

  • Q12

    Does a final budget review with the owner happen before the contract amounts are filled in?

Workflow-wide

  • Q2

    [P1-P7] Do we split this at the pre-construction agreement, with Phases 1 to 3 as unpaid bidding and 4 to 7 as paid pre-construction?

  • Q3

    [P2, P5] Who owns the budget, scopes, bid requests, and the schedule, and when does a super step in?

  • Q10

    [P2, P3] Should QuickBooks be added as the accounting system behind Adaptive?

  • Q13

    [P6, P7] Does whoever runs a takeoff also price it and enter it into the final budget?

  • Q15

    [P2, P3] Should allowances become a signed exhibit with amounts by category and a selection deadline?