Groundwork starts on site
Construction Start
Schedule Activation Process
Working schedule live and being revised
Long-Lead Procurement Process
Weekly Operating Cycle
Look-Ahead Preparation Process
Monday morning
Look-ahead sheet ready for review
Items surface during the week
List current and worked down
Look-Ahead Review Process
Look-ahead meeting starts
Carryover items identified
Prior week reviewed
Coming week's plan agreed
Working Schedule Revision Process
Trade finishes on site
Actual duration recorded on the line item
Week's actuals recorded
Working schedule current for the coming week
Working schedule revised
Variance against baseline visible
Working schedule diverges from the client-facing milestones
UNKNOWN — no source describes how or whether the owner is ever told the revised completion date
Trade Scheduling Process
Trade's start date approaching within their lead time
Trade contacted and given their window
Trade due on site within the confirmation window
UNKNOWN — no confirmation artifact or threshold defined
Material Ordering Process
Coming week's trades and stages set
Orders placed for the week's work
Order blocked on a missing dimension or quantity
Quantity returned and order placed
Owner Communication Process
Owner meeting cadence comes due
Owner briefed and open items captured
Owner or architect conversation starts
Conversation recorded and transcribed
Scope change identified on the job
Change order in front of the owner for approval
Daily Field Cycle
Morning Preparation Process
Superintendent arrives at the office
Overnight email triaged and actions captured
Laborer list runs short
Each laborer has work queued for the shift
Day's plan set and issues outstanding
Open issues raised and direction taken
Site Opening Process
Superintendent arrives on site
Site open, secure, and materials confirmed
Site opened
Attendance known and every absence reached and documented
Site Walk and Quality Control Process
Site opened and trades working
UNKNOWN — no source defines what a completed checklist walk covers
Defect or instruction identified on the walk
Instruction marked on the work for the trade
Site walk reaches each trade's work area
Progress and blockers known for each trade
Site walk in progress
Progress photos captured for the day
Subcontractor Coordination Process
Trade calls or texts during the day
Question answered or action taken
Trade raises a question or problem on site
Question resolved and the trade unblocked
Sub needs a task list and will not use email
Checklist shared and visible to the sub
Day Close Process
Trade finishes for the day
UNKNOWN — no reporting standard or channel defined
Day's work reviewed against the plan
Each shortfall raised with its trade
Day's shortfalls raised
Next day's requirements arranged
Site day ends
Daily log posted, or skipped for the day
Daily log written
UNKNOWN — required fields not defined and ownership of the standard unresolved
Plan Review Process
Upcoming trade or stage approaching
Plan questions identified and routed
Next trade's start date approaching
Site and materials ready for the incoming trade
Afternoon office block
Budget position understood against commitments
Site Preparation and Groundwork
Demolition Process
Site prep starts on a site with existing conditions
Demo scope and price agreed with the contractor
Demolition underway
Demo questions answered and the day's progress confirmed
Survey and Layout Process
Surveyor arrives on site
Survey points handed over and work underway
Trade due to install to a plan location
Locations marked on site for the trade
Building Pad and Foundation Process
Site staked and cleared
Pad graded to the planned elevation
Pad graded
Elevation confirmed correct for the building set
Footings dug and squared
Below-slab utilities and plumbing installed
Pre-Cover Verification Process
Below-slab work reported complete
Installed positions verified against the plans
Work verified and ready for inspection
City inspection held and work cleared for cover
Verification finds work out of position
Discrepancy corrected before cover
Structural Build
Framing Coordination Process
Multi-building job reaches framing
Framing sequenced per building on the working schedule
Framing section reported complete
Hardware verified present and correct
Pre-Cover Verification Process
Progress Documentation Process
Insulation due and rough-ins complete
UNKNOWN — no source states where the pre-insulation record is filed
Condition needs a visual record
Photo captured and sent or filed
Finish-Out and Punch Transition
Finish Material Kickoff Process
First delivery of a finish material with a supplied installation system
UNKNOWN — no kickoff format, attendee set, or trigger threshold defined
Installing crew arrives on site
UNKNOWN — no briefing standard defined
Finish Trade Quality Control Process
Finish trade reports work complete
Work accepted or defects marked before cover
Detail miss identified in finish work
Miss raised with the crew lead and rework agreed
Punch Transition Process
Finish trades report complete
Site released to the cleaning crew
Cleaning starts on site
UNKNOWN — the completion condition depends on the unratified cleaning-start versus cleaning-finish boundary
Notes & Assumptions
Sources and confidence
- Main sources: Tom Kirk interview 2026-08-05 (TOM-F18 to TOM-F46, TOM-F57, TOM-F58) and Connor Fields interview 2026-08-06 (CON-F16 to CON-F32).
- Schedules, look-ahead, to-do sheet, laborers, calls, daily log: TOM-F24, TOM-F25, TOM-F30, TOM-F34, TOM-F36, TOM-F38, TOM-F39, TOM-F43, CON-F15.
- Owner-facing schedule: OFF-F56, DISC-F28. Reporting hours: TOM-F1, STACK-F1.
- Daily cadence and build stages: CON-F16 to CON-F29, CON-F31, OFF-F60 to OFF-F62.
- Look-ahead, log standard, Asana projects, client schedule: OFF-F55, OFF-F56, OFF-F63 to OFF-F65. Pre-construction end state: OFF-F45, OFF-F46, OFF-F49.
- Constraints and client contact: DISC-F1, DISC-F2, DISC-F10, DISC-F16, DISC-F19, DISC-F23 to DISC-F25. Capture gap: STACK-F1 to STACK-F4, STACK-F50.
- JobTread and Quo: operator confirmation 2026-08-25. QuickBooks is pending W1 Q12.
Structure notes
- The weekly cycle (Phase 2) and daily cycle (Phase 3) are defined once and run through all three build stages (Phases 4 to 6).
- The Superintendent owns both sides of every phase boundary. Processes 2.2 and 2.6 belong to the Principal.
- Four hand-overs inside the map: into Phase 1, both ways at the Monday review (2.2), to the Office Manager (2.5.2), and to the Owner (2.6.3). Nobody has described what makes any of them done.
- These steps also support work elsewhere: Monday review, trade scheduling, owner updates, pre-cover checks, and cabinet delivery.
- Process 6.1 has its `SOP checklist:` at process level because neither of its activities is done today.
- Change orders are named but not mapped. Only the routing step exists (2.6.3).
Tool transitions
| Current tool | Field-execution role | Transition | Notes |
|---|---|---|---|
| Asana | Tasks, to-do list, daily log, change orders | JobTread | Finishing jobs stay in Asana through punch. |
| Instagantt | Working schedule | JobTread | Gantt is built in. |
| Google Sheets look-ahead | Monday look-ahead | JobTread | |
| Personal-cell calls and texts | Sub coordination, nothing recorded | Quo | Records and transcribes each call. Open: port numbers or start fresh. |
| iMessage group texts | Subs, internal team, clients | Quo (external), Slack (internal, timing open) | End goal: no internal texting. |
| Client communication channel | Owner updates, change orders | Slack (proposed, timing open) | Until Slack, clients stay on iMessage. |
| Shared iPhone Notes checklists | Task lists for subs who avoid email | No decision | |
| Paper to-do sheet | One super's weekly list | No decision | |
| Granola | Recording owner and architect meetings | Staying | Task sync will change with JobTread. |
| Google Workspace (Gmail, Drive) | Email, documents | Staying | |
| Adaptive | Job cost | Staying | |
| On-site cameras | Site monitoring | Staying | |
| ConX under Houzz | Takeoffs | No decision | One super prefers Bluebeam. |
QuickBooks is not in this table. See the office bidding map, W1 Q12.
Divergences between superintendents
| Topic | Tom Kirk | Connor Fields | Working state in this map |
|---|---|---|---|
| Schedule model | Three schedules: baseline, padded owner version, tight working schedule (TOM-F24, TOM-F25) | One schedule, adjusted to actuals (CON-F15) | Both at 1.1. |
| Running to-do list | Paper sheet | Asana project | 2.1.2. Q5. |
| Site arrival | Unlocks doors, walks site | Subs already in with a gate code | 3.2. |
| In-house laborers | Daily list per laborer | Never mentions laborers | 3.1.2. Q6. |
| Physical marking | Blue tape | Spray paint | 3.3.2. |
| Daily walk | Blue tape plus photos | Construction checklist | 3.3.1. Q8. |
| Look-ahead horizon | Month, two weeks, one week, three days, day before | One week firm, two weeks loose | 2.1.1. |
| Daily log | Two or three times a week | Frequency not stated | 3.5.4. |
| Day length | Seven to five or six thirty | Seven to five or seven | Phase 3. |
| Granola maturity | Uses it, filters output | Not yet using it | 2.6.2. |
| Pre-construction appetite | Did the full pass | Left out, and prefers that | Out of scope. |
| Punch boundary | Punch-workflow concern | Cleaning start, then agreed to cleaning finish | Phase 6, 6.3.2. Q1. |
Assumptions to verify
- Principal is used for Patrick Struble. Owner is the developer client. Q4.
- Office Manager is Lisa Mello. Her surname appears as both Mello and Morel.
- Superintendent is one role covering Tom Kirk and Connor Fields.
- None of the four hand-overs has a stated done check. Q18 and Q20 propose two.
- Failure paths are mostly missing from the sources. Q17.
- The schedule-performance bonus has no written terms.
- No source confirms a preserved baseline comparison exists today (1.1.1, 2.3.3).
Sub-function assignments
| Tentative sub-function | Before condensation | After condensation | Current, after canonical re-homes |
|---|---|---|---|
| Schedule Management | 13 | 11 | 10 |
| Site Supervision | 21 | 19 | 19 |
| Trade Coordination | 15 | 13 | 13 |
| Material Procurement | 4 | 4 | 2 |
| Field Reporting | 6 | 6 | 6 |
| Client Communication | 3 | 3 | 3 |
| Crew Management | 1 | 1 | 1 |
| Build Sequencing | 3 | 2 | 2 |
Small groups may fold; large ones may split.
Naming rewrites
| Original phrasing in source | Applied title | Rule fired | Verb inferred? |
|---|---|---|---|
| "speak the patrick if he needs anything" | Raise open issues and blockers before leaving the office | No roles in titles | "raise" |
| "hit some emails early on to see what's come in" | Triage overnight email for supplier and architect items | Action verb first | "triage" |
| "me reaching out to them, asking why is this not done" | Chase incomplete work with the responsible trades | Action verb first | "chase" |
| "Change orders, the owners" | Route change orders to the owner for approval | Action verb first | "route" |
| "we have a daily to-do list for each of the laborers" | Load the daily task list for each in-house laborer | Action verb first | "load" |
| "I got three separate buildings. So I've got three separate framing" | Sequence framing separately for each building on site | Action verb first | "sequence" |
| "The baseline schedule … then my schedule … best case scenario" | Convert the baseline schedule into the tight working schedule | Action verb first | "convert" |
| "schedule only the owners see … pushed out a little bit further" | Produce the padded client-facing milestone schedule | Action verb first | "produce" (now in Pre-Construction 4.3.1) |
| "different workers … trying to fix something" plus "communication with the sub boss" | Escalate detail misses to the subcontractor's crew lead | Action verb first | "escalate" |
Eight of these are still in this map (Q16). The merged title at 3.2.2 is Q25.
Quality checklist
- [x] Titles follow the naming rules.
- [x] Six phases. Every process has a role, trigger, and end state.
- [!] Processes 1.2 and 5.2 point at other definitions. Process 6.1 has no active activity (Q21).
- [!] Four hand-overs, none with a done check. Nine UNKNOWN end states. Some decision points show one branch only (Q17).
- [x] Status: 56 activities, 48 active, 2 draft, 6 gap. 26 questions, one `?` each.
All open questions (26)
Phase 2: Weekly Operating Cycle
Jump to phase ↑- Q3
Should we add a step that tells the owner a revised completion date?
The client schedule is never updated.
- Q4
Is Principal the label you want for yourself in the ops map?
- Q5
Should one to-do method become the Slate standard going into JobTread?
Tom uses paper, Connor uses Asana.
- Q7
Should we design the per-sub pre-arrival checklist as part of this engagement?
- Q10
Should change orders get their own workflow map?
No source describes how one starts, gets priced, or gets approved.
- Q11
Should look-ahead prep move to Friday?
You said you would prefer a Friday sweep.
- Q13
Do you want an interim client-communication decision before JobTread go-live?
Until Slack, clients stay on iMessage.
- Q14
Does the two-project split (client-facing and internal) need to carry into JobTread?
- Q15
Should the Granola-to-task sync be treated as live, or held as draft until JobTread is set up?
- Q17
Should we do a dedicated pass on failure paths before the gap analysis?
Nothing describes a sub going bust, weather, or a late delivery.
- Q18
For the Monday review, is "the week's plan is agreed and carryover items are named" the right done check?
- Q20
For takeoffs sent to the Office Manager, is "the quantity is back on the task and the order can be placed" the right done check?
- Q22
Does your Monday look-ahead name what is blocking each task and who clears it?
That is typical in custom residential work.
Phase 3: Daily Field Cycle
Jump to phase ↑- Q2
Do you want to set the daily-log standard yourself?
Today there is no standard.
- Q6
Does Connor's job have in-house laborers with daily lists?
Tom keeps one per laborer.
- Q8
Is Connor's construction checklist a real standing list, separate from the punch list?
- Q12
Do the superintendents review job budgets during the build today?
You said you do nearly all of the budget.
- Q16
Do the eight titles in the naming table describe the work the way you would say it?
- Q23
Should the daily log always show weather, each trade and headcount, work done, deliveries, and delays?
- Q25
Do the seven folds listed at the top of this map match how the supers would describe the work?
Phase 4: Site Preparation and Groundwork
Jump to phase ↑- Q24
Should below-slab work get a photo record before the pour, like the pre-insulation video?
Phase 5: Structural Build
Jump to phase ↑- Q26
Where should the pre-insulation video be filed?
Today it may exist only on a phone.
Phase 6: Finish-Out and Punch Transition
Jump to phase ↑- Q1
Should cleaning start be the confirmed punch boundary?
Connor first said cleaning start, then agreed to cleaning finish.
- Q9
Should the supplier install kickoff become standard for every supplied finish system, not just cabinets?
- Q19
Does the superintendent build an outstanding-items list before cleaning starts?
- Q21
Is it true that nothing happens on cabinet delivery day today beyond install starting?